Well,
I spent too much time on these forms. There is so much I didn't
know and so much time and money I could have saved myself
if I did know, but that's life for ya! In the desert, the
ground is so hard, that concrete can be poured right into
the trench, as long as the trench is the right size and below
ground. But I didn't know, so I put forms in all the trenches.
You can see the black plumbing pipes sticking up, also. Before
the foundation is poured, the ground (rough-in) plumbing has
to be laid beneath the foundation, inspected and approved.
|